Hydro-Québec wind plans face new farmland hurdles

Hydro-Québec’s plan to rapidly expand wind power is facing increased uncertainty after agricultural land protection decisions affected proposed wind projects in Quebec.

hydro-quebec: Hydro-Québec wind plans face new farmland hurdles

Hydro-Québec’s plan to rapidly expand wind power is facing increased uncertainty after the Commission de protection du territoire agricole du Québec modified its preliminary position on the proposed Arthabaska wind farm and rejected another project on high-quality farmland.

The developments have raised questions about how Quebec can add large amounts of renewable electricity while protecting agricultural land and maple stands.

Hydro-quebec: Arthabaska project remains only partly authorized

The CPTAQ’s latest notice, dated November 12, 2026, maintains partial approval for the Arthabaska wind project in the Centre-du-Québec region.

The commission authorized the locations of 30 wind turbines and the project’s electrical substation, but continued to refuse the locations of 12 other turbines, a wind-measurement mast, temporary crane crossings and some sections of the collector network.

The proposed project is located across parts of Kingsey Falls, Saint-Albert, Sainte-Clotilde-de-Horton, Sainte-Élizabeth-de-Warwick, Victoriaville and Warwick.

Hydro-Québec lists the project as being under evaluation, with a proposed capacity of 265.2 megawatts and an expected operating period beginning in 2029.

The CPTAQ said the main concerns involved the placement of infrastructure on cultivated land, the effect on farming activities and the use of access roads and underground collector lines outside public rights of way.

The commission also considered concerns about possible stray electrical currents and their effects on cattle operations.

Its modified orientation included 11 conditions, including agronomist supervision during construction, dismantling and restoration work.

The commission has allowed a further 10-day period for written observations before issuing its final decision.

Under the CPTAQ process, a modified preliminary orientation can be followed by additional submissions from interested parties before the case is concluded.

Farmland protection is becoming a central test

The Arthabaska case follows a final CPTAQ refusal involving the proposed Les Jardins wind project in the Montérégie region.

The commission rejected authorization for 21 turbines on September 10, 2026, citing the importance and quality of the agricultural land involved.

The decision has become a significant reference point for developers because the project was proposed in one of Quebec’s most productive farming areas.

The CPTAQ has said it does not apply a separate legal test specifically designed for wind turbines, but evaluates applications according to the characteristics of each territory and the requirements of Quebec’s agricultural protection law.

Maple stands are another sensitive issue.

Environmental documents for the Arthabaska project identify more than 1,823 hectares of maple stands within protected agricultural territory in the project area, although that figure describes the broader study area rather than land that would necessarily be cleared for turbines or related infrastructure.

Those decisions have intensified the debate over whether future wind farms should be concentrated on public, forested or northern lands rather than agricultural areas closer to existing transmission infrastructure and electricity demand.

Hydro-Québec still needs new electricity

Hydro-Québec continues to identify wind power as a major source of new electricity.

Its current strategy says more than 10,000 megawatts of wind capacity could be added by 2035, while the utility currently reports about 4,000 megawatts of installed wind capacity in Quebec.

In April 2026, Hydro-Québec launched a call for tenders targeting between five and 10 terawatt-hours of new wind energy, equivalent to roughly 1,500 to 3,000 megawatts of installed capacity.

The first round is intended for projects that could begin operating between 2031 and 2035, with the first submission deadline set for February 26, 2027.

The tender documents place greater emphasis on Quebec content, local economic benefits and social acceptability.

They also update the reference framework for locating wind farms on farmland and in wooded areas, including maple stands, and give added weight to projects that minimize the use of higher-quality agricultural land.

Only projects supported by resolutions from the municipalities concerned can proceed through the current tender process.

That requirement gives municipalities a more visible role, although projects must still pass provincial environmental and agricultural reviews.

What happens next

The immediate next step for Arthabaska is the CPTAQ’s final decision after the additional observation period.

A final authorization could allow the developer to revise the project again, while a refusal of key components could require further redesign or reduce the project’s planned capacity.

Hydro-Québec’s broader wind strategy is unlikely to end, but the approval process may shift toward projects with fewer conflicts involving cultivated land, maple production and local farming operations.

The utility has also begun studying wind potential in regions such as the Saguenay–Lac-Saint-Jean, Portneuf and eastern Quebec areas.

Hydro-Québec says its newer model is based on partnerships with municipalities and Indigenous communities, with large projects developed alongside local partners and smaller projects selected through competitive tenders.

For Quebec’s electricity planning, the challenge is now twofold: securing enough new generation for rising demand while ensuring that wind projects can obtain the local, agricultural and environmental approvals needed to be built.

Frequently Asked Questions

What changed in the Arthabaska wind project review?

The CPTAQ modified its preliminary orientation by authorizing 30 turbine locations and the electrical substation while continuing to refuse 12 turbines and several related infrastructure components.

Has the Arthabaska wind project received final approval?

No. The latest notice is a modified preliminary orientation, and interested parties were given an additional period to submit written observations before a final decision.

Why is farmland important in Quebec wind project approvals?

Quebec’s agricultural protection system is designed to preserve farmland and agricultural activities, so proposed wind infrastructure must be assessed for its effects on cultivated land, maple stands and farm operations.

How much new wind power is Hydro-Québec seeking?

Hydro-Québec’s 2026 tender targets five to 10 terawatt-hours of wind energy, equivalent to approximately 1,500 to 3,000 megawatts of installed capacity.

When could the next wind projects begin operating?

Projects selected in the first round of the 2026 tender are intended for commissioning between 2031 and 2035, subject to approvals and construction.

Fact-Checked: Key project details, Hydro-Québec’s procurement targets and the CPTAQ review process were checked against official Hydro-Québec, Quebec government and CPTAQ information.

Disclaimer: The Arthabaska project remains subject to a final CPTAQ decision and other required provincial approvals.

Discover more from CTC News

Subscribe now to keep reading and get access to the full archive.

Continue reading

4 New CRA Benefit Payments Coming In November 2026

New Canada Workers Benefit Increase Coming In 2027

New Service Canada Benefit Payments Coming In November 2026

8 New Ontario Laws And Rules Coming In November 2026